Design team: middle school construction moving into construction documents; substantial completion targeted January 2028
Mar 9, 2026
Design and district officials said the Pojoaque Valley middle school project is entering construction-document work, with PSFA/PSCOC award-language adjustments clarified and an anticipated building substantial completion around January 2028; a small adjacent land-swap parcel may require district-funded paving.
The full story
Design representatives told the school board the middle school project is "full steam ahead on the design" as it moves from design development into the construction-document phase, a five-month block the team said is being padded with extra contingency weeks for PSFA review.