Highway supervisor reports paving and chip-and-seal progress, wind/solar project work
Summary
Highway Supervisor John Pluimer told the council on Sept. 3 that paving on Marsh Road is projected to be completed, five miles remain for chip-and-seal in Jackson Township, concrete bases are being poured for wind projects, and solar companies are delivering materials.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Highway Supervisor John Pluimer briefed the council on ongoing road and project work, saying paving on Marsh Road was projected to be completed and five miles remain for chip-and-seal in Jackson Township. Pluimer also said crews were pouring concrete bases for wind projects and that solar companies were bringing in significant materials to county roads.
Pluimer flagged damage to Road 100 W that resulted from road closures associated with project traffic; no specific repair estimate was provided at the meeting. The council recorded the update as part of routine departmental reporting; no action or funding authorization followed immediately from Pluimer’s report.