Staff seeks CMGC approach, reports CDOT concurrence for Happy Canyon interchange

May 27, 2025

Staff briefed council on design alternatives for the Happy Canyon interchange, said CDOT and partners concurred with using a construction manager/general contractor (CMGC) delivery method, and noted the project's TDM report reached a 1.8% reduction versus CDOT's 3% target for more urban interchanges.

The full story

The presentation on the Happy Canyon interchange described the project's environmental and delivery planning and why staff are pursuing a construction manager/general contractor (CMGC) approach. "Wednesday of this week, we got concurrence from CDOT RTD to go ahead and do a CMGC," Rebecca said, noting the approach allows a contractor to participate in design for constructability and cost savings.