AEP reports pole replacements, route‑mile progress in Patrick County fiber build
May 27, 2026
May 27, 2026
Appalachian Power told Patrick County officials that 314 miles of fiber have been built system‑wide and 148 miles in Patrick County; AEP reported 819 poles needing replace across the project (243 in Patrick County) and provided estimates for remaining route completion.
The full story
An Appalachian Power (AEP) representative updated the Patrick County board on the company’s portion of the multi‑county fiber backbone, describing progress on construction, pole replacements and point‑of‑presence sites.