Union 13 check plans cleared by IDOT; STIP revision required after cost increase
Jul 27, 2026
Jul 27, 2026
IDOT cleared check plans for the Union 13 project with minor corrections; county staff are working on easements and a STIP revision because the project cost increase exceeds 30%, and the revision will be presented for policy-board approval in September.
The full story
County Engineer Jared Johnson told the board that IDOT cleared check plans for the Union 13 project with only minor corrections and that staff are working to obtain necessary easements for the project's structure.