Council approves final payment and $71,000 decrease for Highway 12 water-main project

Nov 12, 2025

The City of Montrose approved the final payment application and change order for the Highway 12 water-main replacement; the change order reconciles final contract quantities and reduces the contract by $71,000, city engineer Jared Vogi told council.

The full story

The City of Montrose council approved the final payment application and a change order for the Highway 12 water-main replacement project at its Nov. 10 meeting.