Council approves final payment and $71,000 decrease for Highway 12 water-main project

City Council, City of Montrose · November 12, 2025

Summary

The City of Montrose approved the final payment application and change order for the Highway 12 water-main replacement; the change order reconciles final contract quantities and reduces the contract by $71,000, city engineer Jared Vogi told council.

The City of Montrose council approved the final payment application and a change order for the Highway 12 water-main replacement project at its Nov. 10 meeting.

City Engineer Jared Vogi said change order No. 1 reconciles final contract quantities and reduces the contract amount by $71,000. He recommended approval of the final payment and the change order, and council members moved and voted to accept the recommendation. “Ultimately, what change order number 1 does is it reconciles the final contract quantities and costs to the contract amount, and it is a change order, decrease in the amount of $71,000,” Vogi said.

The packet included final closeout documents such as consent surety and lien waivers, which staff said were in order. Council approved the payment and change order by unanimous vote. Staff said this action completes the project closeout steps in the packet; no further timeline or outstanding contractor claims were raised during the discussion.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source