Staff proposes uniform project‑segmentation standard for three SB 1 programs

Jul 27, 2026

Staff presented a single segmentation standard to apply to the Local Partnership Competitive Program, Solutions for Congested Corridors Program and Trade Corridor Enhancement Program: segments must meet purpose/need, have independent utility, connect logical termini and not limit alternatives; nominations must show benefits and full funding for each segment.

The full story

Naveen Habib walked through proposed changes to project‑segmenting language that would standardize requirements across three SB 1 programs. He defined a "segment" as a portion of a project with independent utility and contrasted it with a "work package," which is a contracting bundle that need not have independent utility.