County engineer reports progress on multiple bridge and paving projects

Jackson County Board of Supervisors · July 7, 2026

Summary

The county engineer told the board crews are completing bridge rails, grading and paving work on several projects (450th Avenue, Springbrook Highway bridge, Bernard Road) and that river levels are affecting work on the Copeland/Channelworth bridge; most projects expect openings in the coming weeks subject to weather.

Jackson County Engineer Jaden Sheck updated the board on active construction. He said rails had been poured on a 450th Avenue bridge near Preston, grading and riprap work were scheduled, and paving crews were sequentially completing lane work on the Springbrook Highway bridge approaches. He cautioned that final dates are weather-dependent and dependent on subcontractor schedules.

Sheck also said Channelworth/Copeland River work has substructure and piers in place but that high river levels are delaying beam-setting operations. He noted the Bernard Road paving project was progressing well and expected to be wrapped up within days, barring weather or plant issues.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source