Engineer reports progress on AMD, Chub Run and other infrastructure projects

Town of Nutter Fort Council · August 26, 2025

Summary

Engineers reported Phase 1 AMD is finalizing pay-application comments and may be ready for drawdown at the September meeting; Phase 2 has 20 of 34 ROWs secured and awaits environmental clearance from OSM before bidding; Chub Run remains on hold with a potential Oct. 1 start; Phase IV awaits DEP clearance for Sandy's Hardware forcemain work.

The town engineer provided a multi-item update on Aug. 26. Phase 1 of the AMD project is completing pay-application comments and is expected to be ready for drawdown at the September council meeting. For Phase 2, the engineer reported 20 of 34 right-of-ways are in hand and the project is awaiting an environmental assessment clearance from OSM; the item was described as likely to go out to bid by the end of the year.

Chub Run remains on hold, with a potential Oct. 1 start identified; the engineer presented RPR resumes for discussion and noted that rates were being adjusted to cover debt-service-related level adjustments. Phase IV is waiting on an environmental clearance from DEP for Sandy's Hardware forcemain work. The engineer also noted that Task Order 7 permitting for Nutter Run is complete.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source