Engineer reports progress on AMD, Chub Run and other infrastructure projects

Aug 26, 2025

Engineers reported Phase 1 AMD is finalizing pay-application comments and may be ready for drawdown at the September meeting; Phase 2 has 20 of 34 ROWs secured and awaits environmental clearance from OSM before bidding; Chub Run remains on hold with a potential Oct. 1 start; Phase IV awaits DEP clearance for Sandy's Hardware forcemain work.

The full story

The town engineer provided a multi-item update on Aug. 26. Phase 1 of the AMD project is completing pay-application comments and is expected to be ready for drawdown at the September council meeting. For Phase 2, the engineer reported 20 of 34 right-of-ways are in hand and the project is awaiting an environmental assessment clearance from OSM; the item was described as likely to go out to bid by the end of the year.