County engineer reports road projects; bridge design agreement to be signed when received
Sep 22, 2025
The county engineer reported that the Eagle Drive regrade should finish the day of the meeting, the Douds motor grader is at Altorfer for repair, and the roads crew returned to a five-day schedule; Conservation Director Richard Daugherty said he will have the chair sign the Bentonsport Bridge engineering design agreement once it is received.
The full story
County Engineer Ryne Thornburg updated the board on several secondary roads items: the Eagle Drive regrade was expected to be finished that day, the Douds motor grader has been delivered to Altorfer for repair, and the roads crew returned to a five-day, eight-hour schedule. Thornburg said the next regrade project had not yet been determined and reminded the board that a Dust Pods demonstration was scheduled for Sept. 24.
