Council approves $223,789.39 pay application for Main Lift Station project
Apr 9, 2025
Apr 9, 2025
The council approved Pay Application No. 3 for the Long Prairie Main Lift Station Improvement Project, authorizing payment of $223,789.39 to C&L Excavating and noting the project is about 29.7% complete.
The full story
The Long Prairie City Council approved Pay Application No. 3 for the Main Lift Station Improvement Project on April 9, authorizing payment of $223,789.39 to C&L Excavating. The mayor reported the site visit and noted that the project is progressing; the payment application represents about 29.7% completion of the contract value recorded to date.