Pitman reports completion of Vassar Ave. water-main project; testing passed

Aug 12, 2024

Officials reported the new Vassar Ave. water main was completed and bacteriological testing passed; crews will begin tying service lines to the main. Routine meter work, leak repairs and hydrant flushing were also reported.

The full story

The borough’s Water & Sewer Department reported that the Vassar Avenue water-main replacement has been completed and bacteriological testing of the new main was completed and passed. Staff said they will begin tying individual service lines to the new main this week.