Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
BOCC approves change orders, extends completion dates for two road overlay projects
Summary
Commissioners approved Change Order No. 2 for the Peckham Road Overlay (new completion date Aug. 4, 2026) and Change Order No. 3 for the Enterprise Road Overlay (new completion date July 24, 2026), citing plant shutdowns and schedule adjustments.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
The Board approved Change Order No. 2 on the Peckham Road Overlay Project (Bid #2026-7, District 2) and Change Order No. 3 on the Enterprise Road Overlay Project (Bid #2025-33, Dist#1).
Commissioner Jason Shanks said the Peckham change order "revises the completion date to August 4, 2026" because the Evans and Associates plant was shut down. Commissioner Shane Jones said his Enterprise Road project’s completion date was being revised to July 24, 2026 and noted his project is running ahead of District 2.
Both change orders were approved unanimously. The board did not provide additional cost detail in the meeting record; the revisions were framed as schedule-driven adjustments due to plant availability.
