Committee authorizes $50K contract authority increase for 2024 ADA retrofit program

Aug 3, 2026

Staff requested an increase in contract authority for the 2024 ADA curb-ramp retrofit program to cover unanticipated demolition, wall replacement and thicker pavement conditions; the committee voted to forward the increase to the Aug. 11 consent agenda, with staff noting the overall project budget of $585,000 covers the requested $50,000 increase.

The full story

John Cole told the committee the 2024 ADA retrofit program had encountered unanticipated force-account work — including demolition, replacement of walls and added asphalt to accommodate thicker-than-expected pavement — that created cost overruns. He said the total anticipated expenditures were about $429,009.85 and that the requested increase in contract authority was $50,000. "So the request is to increase the contract authority by $50,000," Cole said, adding the overall project budget remains within the previously anticipated $585,000 total.