Point Roberts PUD broadband project faces higher-than-expected make-ready cost; construction planned July 2025
Apr 26, 2025
A PUD broadband project for parts of Point Roberts has a March make-ready quote of about $1,100,000, county right-of-way permits are complete, a PSE pole-attachment permit is pending, and construction is targeted to begin in July 2025; a separate grant may cover roughly 400 additional homes pending May finalization.
The full story
The Point Roberts Community Advisory Committee received an update on the PUD broadband rollout on April 17, with committee member Jared reporting the project is 'underway' but that make-ready costs came in higher than expected.