County reports progress—and sand buildup—from heavy rains on Talleywash project

Aug 4, 2026

County manager said heavy rains brought 2–3 feet of sand build-up in culverts affecting the Talleywash project; crews performed cleanup and dewatering and staff said the project was roughly four to five weeks from completion.

The full story

Dustin updated the board on work at the Talleywash project, reporting heavy rains had caused about 2–3 feet of sand accumulation under culverts and required cleanup and road rebuilding in places.