Owyhee school construction proceeds; district seeks roughly $9–9.5 million for phase two

Elko County School District Capital Projects Oversight Panel · March 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent Clayton Anderson reported that structural steel, framing and second-floor concrete are in place for the Owyhee combined school (phase 1); phase 2 — including a CTE building, transportation facility and parking — needs about $9–9.5 million more before bidding will begin.

Clayton Anderson updated the committee on the Owyhee combined school construction project and said phase 1 is progressing well.

"Most of the school's structural steel has been placed. The exterior walls are being framed. Second-floor concrete is poured. Roof is being installed. Electrical, plumbing, HVAC — so they're all starting to move forward installing their equipment," Anderson said, summarizing on-site progress. He added the district is collaborating with the tribe on utilities and potential matching donations to enable a second phase of the project.

Phase 2 would include a career and technical education (CTE) building, parking, a transportation building and fueling facilities; Anderson said the district estimates the additional funding need at approximately $9 to $9.5 million. He emphasized the district will not begin bid or procurement steps for phase 2 until that funding is in hand.