County clears contractor to start Hamrick Ridge bridge work; materials ordering to begin
Summary
The commission authorized Battle Ridge Builders to proceed with the Hamrick Ridge bridge replacement so the contractor can order materials; staff warned steel bridges may have multi‑month lead times.
Get email alerts on the Bridges topic
No spam. Unsubscribe anytime.
Park County authorized Battle Ridge Builders to proceed with the Hamrick Ridge bridge replacement project and to begin ordering materials so work can proceed when the bridge components arrive. Roads staff said the existing bridge is closed because it cannot structurally carry weight, and that contractors will order the steel components and begin preparatory work as timelines allow.
Staff explained steel bridges have long lead times and estimated vendors were currently quoting about four months for a steel bridge. "So in this situation where the bridge is already closed because it can't structurally handle any weight, they can actually start work earlier than they get the bridge," a roads representative said. Commissioners approved moving forward so the contractor can order materials and schedule installation.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.