Engineer: Pinehurst inlet grate replacement near completion; storm exceeded design rainfall
Aug 27, 2024
District Engineer Charlie Krebs said MRI's Pinehurst inlet-grate project is about 80% complete, the storm system reached capacity after nearly 8 inches of rain in two to three days (roads designed for 5½ inches in 24 hours), and staff may add a drainage connection to direct runoff into the lake.
The full story
District Engineer Charlie Krebs told the River Ridge board on Aug. 27 that the MRI project to replace Pinehurst valley gutter inlet grates is about 80% complete and he will follow up on the schedule for the asphalt patch. Krebs said parts of the community received nearly 8 inches of rain in two or three days during Tropical Storm Debbie, exceeding the roads' 24-hour design capacity of 5½ inches.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →