Henry County updates: Clover bridge reopened; Kewanee, Cambridge and Galva projects underway

Apr 9, 2026

County Engineer Scott Stephenson told the Transportation Committee the Clover Township bridge is complete and open, Kewanee work has started with an estimated 30 working days to completion, Cambridge is scheduled to start late April and Galva repairs will begin in May.

The full story

At the April 9 meeting Scott Stephenson reported that the Clover Township bridge project has been completed and is open to traffic. "Clover Township Bridge project has been completed and is open to traffic," Stephenson said.