VDOT reports 92.4% completion on recent maintenance work orders; several projects planned
Aug 4, 2026
VDOT told the board it completed 268 of 290 maintenance work orders (92.4% completion) for the quarter, outlined patching and pipe repairs, and previewed larger projects including a Morris Ferry bridge deck award and Route 58/I-95 replacement expected in coming months/years.
The full story
A VDOT representative (speaker 11) gave a detailed quarterly maintenance report: 268 of 290 work orders were completed, leaving 22 outstanding and reflecting a 92.4% completion rate for the period April 1–June 30. The presentation noted common maintenance needs—pothole patching, ditching, pipe repairs—and described an upcoming plant-mix patching contract set to begin the following day.