Construction progress reported for Moss Elementary and campus projects; gas line is critical path
Jan 13, 2025
District construction staff reported Moss Elementary has permanent power and RTUs installed; final interior finishes await a gas line from Atmos (expected in about two weeks), with sod and playground work planned for mid-May.
The full story
The district’s construction representative reported progress across the ongoing campus projects, focusing on Moss Elementary. The speaker said permanent power is on site and rooftop units are in place; the remaining critical path item is a gas line from Atmos, which is expected to arrive in roughly two weeks and will allow interior finishes and flooring to proceed.