Engineers propose revised sheet‑pile alignment to avoid removing several gangways

Belvedere Seawall Subcommittee · May 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Design team presented a revised, more surgical sheet‑pile alignment that would minimize gangway removals and utility disruptions by placing some piles under the sidewalk rather than through gangways; the option must be weighed against geotechnical toe‑protection needs and cost.

Engineers explained that the original design extended the sheet‑pile alignment past multiple gangways and required reinforced beams and significant utility relocations. Tony Boyd said the geotechnical review and cost estimates made that outboard alignment less attractive and staff have developed a revised alignment that keeps much of the work behind the seawall or under sidewalks.

The revised plan would remove fewer gangways and preserve resident access longer during construction, but staff said it must be cost‑effective and provide required toe protection at the most eroded sections of the wall. Committee members asked for cost comparisons and contractor input; staff said design sketches and unit prices are being prepared for review before the next meeting.