Phase 2 interior work 74% complete, board hears; contingency balances reported

Oct 14, 2024

Project superintendent reported Phase 2 interior punch-list work is underway and that the phase is 74% complete with $431,606 in construction contingency and $123,351 in owner contingency. District aims to move into Phase II spaces Oct. 24.

The full story

The Veribest ISD board on Oct. 14 received a construction update that placed Phase 2 at roughly three-quarters complete.