Phase 2 interior work 74% complete, board hears; contingency balances reported

Board of Trustees, Veribest Independent School District · October 14, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project superintendent reported Phase 2 interior punch-list work is underway and that the phase is 74% complete with $431,606 in construction contingency and $123,351 in owner contingency. District aims to move into Phase II spaces Oct. 24.

The Veribest ISD board on Oct. 14 received a construction update that placed Phase 2 at roughly three-quarters complete.

Project Superintendent Jason Bramlett with Gallagher Construction Services reported: "Total Budget Phase 2 $9,696,092.00; total completed and stored to date $7,222,026.00; percentage of completion is 74%; construction contingency balance $431,606.00; owner contingency balance $123,351.00." Bramlett said the remaining interior punch-list items are in progress.

Superintendent Mandy Traylor and project staff discussed sequencing for move-in and outstanding corrective work. The district confirmed a target move-in date for Phase II spaces (furniture delivery projected Oct. 24) and said remaining work would be managed so instructional activities could begin on schedule.