Wilton Select Board hears waterline update; project expected to finish by November

Aug 5, 2026

Public works presenter Jim Ward told the Select Board Pratt and Sons has installed most of the new main, connected multiple customers, and completed testing of the finished transmission main; he said the team is "anticipating being fully complete sometime in November."

The full story

Jim Ward gave the board a progress update on Wilton's waterline replacement, saying contractors Pratt and Sons began work in April 2025 and, as of May, had completed about 14,000 feet of new water main and connected customers on Doak Street and Weld Road. Ward said crews completed testing and disinfection of the finished transmission main from the treatment plant to Doak Street and had cleaned up much of the right-of-way.