Engineer says Trapper Road bridge completion delayed weeks after incorrect guardrail brackets ordered
Summary
Zach Olivas of Great River Engineering told the commission the Trapper Road bridge (BRO-R10800(45)) is in its final stages but completion will take a few more weeks because the ordered brackets for the guard rails were not correct.
Get email alerts on the Bridges topic
No spam. Unsubscribe anytime.
The commission received a call from Zach Olivas with Great River Engineering about the final stages of the new bridge on Trapper Road (project BRO-R10800(45)). Olivas estimated completion would take a few more weeks because an order of brackets for the guard rails was not correct.
The minutes record the timeline estimate and the cause of the delay (incorrect bracket order). The record does not show any new motion or budget action to accelerate procurement or change vendors.