Commissioners approve $28,500 change order for Bluegrass Boulevard Phase III

May 11, 2026

A change order for Fillmore Construction on Bluegrass Boulevard Phase III added $28,500 for temporary fence installation and vacuum excavation, raising the contract to $9,687,365.79; the county engineer recommended the change and the board approved unanimously.

The full story

Fayette County approved Change Order No. 1 on May 11 for the Bluegrass Boulevard Phase III Roadway Improvements with Fillmore Construction, LLC. The change order adds $28,500 to pay for temporary fence installation ($26,000) and vacuum excavation for a waterline crossing ($2,500); the adjusted contract total is $9,687,365.79.