Council approves final payment and net decrease change order for Wall Street sidewalk project
Summary
The council approved Payment Certificate No. 3 (final) to Diamond Construction for $8,491.66 and authorized Change Order No. 2 (final), which showed a net decrease of $17,238.76, indicating project closeout and adjustment to the contract.
Get email alerts on the Capital Project Closeout topic
No spam. Unsubscribe anytime.
Councilmember Bray reported that Diamond Construction completed the Wall Street Sidewalk Improvements and that the borough engineer certified final Payment Certificate No. 3 in the amount of $8,491.66. The council approved the final payment and authorized Change Order No. 2, showing a net contract decrease of $17,238.76.
The resolution authorizes borough officials to make payment in accordance with the final certificate and to sign the approved change order, formally closing the contract record for this project.