Santa Rosa ISD: CTE building 50% complete; bond report shows $3.32 million remaining
Oct 21, 2024
Oct 21, 2024
The board received a construction update showing the district's CTE/Early College building is about 50% complete with projected substantial completion March 12, 2025. The 2023 bond report lists a remaining bond balance of roughly $3.32 million.
The full story
Santa Rosa ISD trustees received a construction and bond-allocation update during their Oct. 21 regular meeting. Ernie Villarreal, PMSI bond project manager, told the board the CTE/Early College building has a construction cost of $2,842,564.07 and was listed 50% complete with a contract completion date of March 12, 2025.