Comal County approves structural changes and $3.35M change order for mental‑health unit

Oct 23, 2025

The court approved a small architectural amendment ($3,700) and a larger $3.34–$3.45 million change order for structural corrections at the Comal County mental-health extended observation unit, funded from ARPA interest and remaining project contingency; completion date extended to Oct. 2, 2026.

The full story

County staff told the court that unanticipated subsurface conditions required redesign of the mental‑health unit’s foundation: piers originally designed for about 33 feet must be extended to 50 feet and cased because of groundwater and clay.