Engineer reports Phase IV nearly complete; Phase V on hold
Summary
Engineer Ryan Holcomb told the Nutter Fort council that Phase IV sewer line work is complete with two weeks of concrete/sidewalk remaining and paving to follow; Phase V is on hold. The engineer said a change order for Phase IV will be presented at the next meeting.
Get email alerts on the Sewer Infrastructure topic
No spam. Unsubscribe anytime.
Engineer Ryan Holcomb updated the council on multiple sewer-related contracts during the Oct. 22 meeting.
Holcomb said Phase IV line work is complete; the contractor has about two weeks of concrete and sidewalk work remaining and paving will follow. He said staff will present a change order at the next meeting covering concrete steps, stored materials and quantity adjustments.
Holcomb also reported Phase V sewer work is on hold for the time being. No new dates were provided for resuming Phase V activity.