Minor-subdivision extension approved with specific bond, timeline conditions

Monroe County Plan Commission · August 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission granted SIA-22-18 a one-year extension to 06/30/2027 and required an additional $2,077.79 guarantee plus deadlines for updated documents and right-of-way acceptance applications.

Staff presented SIA-22-18, a column-three lot minor subdivision with previous approvals and a cashier's check on file for $20,777.88. Staff explained that engineered designs for intersection improvements at Walnut Street Pike and Holland Drive had not yet been completed and that driveway designs and drainage-board submissions remained outstanding. The developer requested an extension until 06/30/2027 and agreed to add inflation to the estimate.

Staff recommended a one-year extension to 06/30/2027 with an adjusted inflation amount that increases the guarantee by $2,077.79 to a total shown in the exhibit. Conditions included submitting the additional financial guarantee by 08/28/2026, signing updated performance-bond and subdivision documents by 09/11/2026, and applying for right-of-way acceptance by 05/01/2027. The commission approved the recommendation on a motion and second. The motion passed 7–0.