Commissioners approve drainage change order and multiple construction payments
Summary
The court approved Change Order No. 5 (Hidalgo drainage improvements, 2018 bond project) including a contract increase and 60 additional days, and approved multiple contractor payment applications totaling six- and seven-figure sums tied to county drainage and road projects.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Staff recommended several construction and payment approvals tied to county drainage and road projects. For the Hidalgo drainage improvements (2018 bond project number 13), the court approved change order number 5, which included an increase to the contract price and 60 additional construction calendar days as recommended by the project engineer and assistant GM.
The court also approved progress-payment applications from multiple contractors and consulting firms — including RDH Site In Concrete LLC; Gonzales Engineering Management LLC; Construction Enterprise LLC; Econ Group; and Synergy Development and Construction LLC — across several contract numbers cited in the presentation. Motions to approve the listed payments and the change order were moved, seconded and carried.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.