LAWA board authorizes procurement for construction-manager-at-risk to speed Biota plant work

Lake Agassiz Water Authority · August 7, 2026

Summary

After presentations and extensive Q&A, the authority authorized staff to develop CMAR procurement documents (RFQ/RFP) for the Biota Water Treatment Plant to gain schedule advantages and earlier cost certainty; board members cited Grand Forks examples and range of contractor markups.

Consultants outlined how a Construction Manager at Risk (CMAR) could overlap pre-construction work with design to shave roughly a year off the delivery schedule, enable early bid packages (deep foundations, mass concrete), and produce a guaranteed maximum price during design. "I think we could save about a year off from the design by starting to work with a CMAR contractor," Paul said in the presentation.

Board members asked detailed questions about cost certainty, CMAR markup (presented range 4–10%), statutory procurement steps and examples from Grand Forks and Fargo. Staff emphasized that the RFQ/RFP process is the next step and that multiple board approvals would be required later (selection, pre-construction agreement, and GMP). The motion to develop procurement documents and begin the CMAR selection process carried on a roll call.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source