Selectboard Questions Timeline for Route 100 Culvert Replacement

Town of Weston Selectboard · June 23, 2026

Summary

Weston Selectboard reviewed the Route 100 culvert replacement and asked why contractors could not accept an incentive to finish in seven days versus nine to fourteen; member Jim Linville will follow up with bidders about timeframes and incentives.

The Selectboard reviewed status details for a culvert replacement and roadway closure on Route 100 and asked staff to clarify contractor incentives and timelines.

Board members questioned why an incentive to complete the work in seven days, rather than a nine‑to‑fourteen‑day window, had not been offered to contractors. Jim Linville said he would call for an update on bids and to press on the proposed time frame and incentives to reduce road closure duration.

No bid award or closure decision was made at the June 23 meeting; the topic remains under review and will be revisited when updated bid information is available.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source