District contractor/presenter Raj Patel reported site work is complete, grade beams and fire-lane installed, the first metal components arrived and structure construction will begin; paving and parking work are underway and sidewalks are scheduled in two to three weeks.

The full story

At the Sept. 8 meeting Raj Patel provided an update on the MPSC construction project, reporting that all site work around the building is complete, including grade beams and fire-lane installation. He said the first truckload of metal building components has arrived and that structural construction would begin shortly.