Board accepts completion of Jackson and Wise Elementary bond projects; bond work reported on time and under budget

Aug 21, 2025

Trustees accepted final work on Jackson and Wise Elementary projects and heard a superintendent update that the district completed 11 major projects in an 18-month span, with some retainage remaining and final punch-list items cleared.

The full story

The board approved acceptance of final construction work at Jackson Elementary and Wise Elementary as completed under the district's bond program. A presenter reported the final punch lists had been closed and recommended formal acceptance under district policy.