Engineer reports Phase IV sewer nearing wrap‑up; Route 20 preconstruction scheduled
Oct 22, 2024
Town engineer Ryan Holcomb reported Phase IV sewer line work is complete with two weeks of concrete and sidewalk work remaining before paving, Route 20 Corridor preconstruction is set for Nov. 14, and Phase II AMD's NEPA assessment was resubmitted for final approval.
The full story
Engineer Ryan Holcomb updated the council on multiple capital projects. He said Phase IV sewer line work is complete and the contractor has approximately two weeks of concrete and sidewalk work remaining before paving begins; a change order covering concrete steps, stored materials and quantity adjustments will be presented at the next meeting.