Contractors update Taft ISD trustees on Bond 2024 construction progress

Taft Independent School District Board of Trustees · August 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

AG/CM Mayra Pinon and SpawGlass project manager Justin Caskey told trustees that baseball and softball fields and the agriculture/maintenance/transportation building remain active projects; tennis courts are in demolition and GMP numbers will be presented at the September meeting.

Mayra Pinon, representing the district's agent/construction manager (AG/CM), and Justin Caskey of SpawGlass gave the board an update on Bond 2024 construction at the Aug. 18 meeting. They reported that the baseball and softball fields are still active projects, work on the agriculture, maintenance and transportation building is ongoing, and demolition of the tennis courts is underway.

The presenters told trustees that guaranteed maximum price (GMP) numbers have been received and that staff plan to provide a formal GMP update at the board's September meeting. The presentation focused on construction scheduling and the next reporting milestones; the minutes do not include additional financial detail or timeline estimates.