Committee hears August 11, 2027 contract substantial completion and possible September soft opening
Aug 6, 2026
Aug 6, 2026
Project schedule presented to the committee shows a contract substantial completion date of August 11, 2027; presenters outlined how furniture and technology procurement will be coordinated and discussed a tentative soft opening around September 1, 2027.
The full story
Peter presented the contractor's critical schedule and said, "Currently, just the substantial completion date for the project is 08/11/2027," describing that date as the contractually required substantial completion when keys and ownership of the building transfer to the town.