Project budget snapshot: $19M base contract, $3.6M construction contingency
Aug 6, 2026
Aug 6, 2026
Project managers presented a condensed budget dashboard showing a $19 million base bid, pending change orders that bring the contractor total toward $19.5 million, and separate construction and owner contingencies to track construction vs. owner-directed costs.
The full story
Peter, the project presenter, told the committee the dashboard was designed as "one stop shopping for information" and summarized the contract baseline and contingency positions. "The base contract on Row 16, see the 19,000,000," he said, and noted pending change orders would raise the contractor total toward $19.5 million.