Jun 22, 2026

Council considered Bollig Task Orders #8 (Funding Application/Administration) and #9 (Well/Wellhouse Design). The council asked Bollig to remove percentage-based fees from #8 and noted task-order standards and protocol under the engineering master agreement need review; Task Order #9 was listed at $230,000.

The full story

The council reviewed two Bollig task orders during the special meeting. Task Order #8 (Funding Application/Administration) was recorded in the transcript as $5,000 per year plus 5% of funding secured; council members requested Bollig revise that task order to remove percentage-based fees. Task Order #9 (Well/Wellhouse Design) was listed at $230,000.