Board hears bond update; Ryan Intermediate skylight replacement scheduled for June
Summary
Trustee McCann's bond report—delivered by Board President Carole Mendez—says Bid Pack #1 wish list is complete, Bid Pack #2 storage items largely complete, sinking fund projects finalized except for a Ryan Intermediate skylight replacement planned for June.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
President Carole Mendez reported the bond-project status on behalf of absent Trustee John McCann: Bid Pack #1 wish list is complete; Bid Pack #2 storage facilities are largely complete with a few items remaining. Sinking fund projects have been finalized except for the Ryan Intermediate skylight replacement, which is scheduled for June. The Facilities Committee will revisit the middle school courtyard project and band furniture as funds allow.
No formal vote on bond allocations was taken at the meeting; the board noted remaining bond funds are available and left some project prioritization to the Facilities Committee. The update was presented as a progress report rather than a final action.