Committee hears move schedule and aims for August 24 staff walkthrough
Aug 7, 2026
Project team confirmed an August 24 walkthrough for staff and movers, with an expected admin-area temporary certificate of occupancy within days pending fire alarm and building-inspector signoffs; broader public access is scheduled for October.
The full story
Project staff told the committee that movers (Pioneer) will begin the primary move on Monday, August 24, with the central office moving back on Saturday, Sept. 12. "We are planning to start the move Monday, August 24, with Pioneer. They are expecting that it will take up to 4 to 5 days," Alex said when giving the move update.