District construction update: bond projects progressing; billing at 2.8% through May
Summary
BTC Construction presented progress on 2025 bond projects at Edison, Chalmers and Gainesville Intermediate: permits released, billing at 2.8% through May, and upcoming subcontractor selection and PVC piping installation. Drone photos and schedules were reviewed.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
BTC Construction representatives updated the Gainesville ISD Board on Phase 1 bond projects at Edison Elementary, Chalmers Elementary and Gainesville Intermediate School on June 15.
Scott Barnes, BTC vice president of operations, and Leslie Jimenez, project manager, reported billing for the projects is at 2.8% through May, full permits have been released, and near-term work includes responding to city comments, subcontractor selection and PVC piping installation. Drone photos showing site progress and an overall project schedule were presented; no board action was required.