Lindsay ISD: new elementary building slabs poured, on track for May completion

Feb 25, 2026

Superintendent Steve Cope told the board that concrete slabs have been poured for the new elementary building, permanent electricity will be connected, intercoms are being installed and cameras/doors await ceiling installation; the project is on track for end-of-May 2026 completion.

The full story

Superintendent Steve Cope reported Feb. 25 that construction of the new Lindsay elementary building has progressed to the point that concrete slabs have been poured and permanent electricity will be connected now that the slabs are in place.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or