Twisp council accepts multiple infrastructure project completions; WWTP nearly back on schedule

Twisp Town Council · May 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Director Denham reported the WWTP project is nearly back on its original schedule and the town's solar installation is almost complete. Council approved acceptance resolutions for the Canyon Street project and several wastewater system improvements, mostly on unanimous votes and via the consent agenda.

Director Denham told the council that the wastewater treatment plant (WWTP) project is progressing well and is almost back on the original overall schedule. He also reported the town solar project has nearly all panels installed and should be completed next week.

On action items, Council approved Resolution #25-741 accepting the Canyon Street Project (motion by Council Member Tim Matsui, seconded by Will Menzies; passed unanimously). Resolutions accepting the Collection Systems Improvements Project (#25-742) and the Screw Press Project (#25-743) were approved on the consent agenda and recorded as unanimous; the legal services agreement and WA State Arts Commission grant acceptance were also recorded on consent.